Pathway improvements on Cascade Rd will soon be underway.
Below is the tentative project schedule:
|
Start
|
|
Finish
|
Spaulding and Cascade Rd SE (Mobilization, Traffic Set-up, Removals, Milling, Grading, Aggregate, Misc Relocations, Concrete Flatwork, Paving, and Restoration) |
5/1 |
|
5/31 |
|
|
|
|
Cascade Rd SE and Burton St (Mobilization, Traffic Set-up, Removals, Milling, Grading, Aggregate, Misc Relocations, Structure Covers, Paving, Restoration) |
6/1 |
|
6/28 |
|
|
|
|
Buttrick Ave SE (Mobilization, Traffic Set-up, Removals, Milling, Grading, Aggregate, Misc Relocations, Pipe, Paving, Restoration) |
6/29 |
|
8/4 |
|
|
|
|
Open to Traffic |
8/4 |
|
|